We are doing major family upgrade on our target Isilon cluster.   We have a couple of policies where the source is of multiple TB and the assosication takes min of 24hrs to complete after it's break.    This will push our maintenance window to near more than a day

Is there any way that to avoid associations from breaking ?    If I disable the policies on source and target,  before upgrade and enable after, Will it resolve the issue of policy breaks and resets ? 

Thank you for your inputs.

300 Posts

June 23rd, 2017 05:00

i always only disable the schedule of the syncIQ policy (source only, since there shouldn't be any Action on target of a policy, so it doesn't start while upgrading)

never had any problems regarding syncIQ.also doens't require any "fullsyncs" or stuff like that.

178 Posts

June 23rd, 2017 06:00

Thank you for the input ☺