Prerequisites
Follow the safety guidelines listed in Safety instructions.
Power off the system and all attached peripherals.
Disconnect the system from the electrical outlet and disconnect the peripherals.
If applicable, remove the system from the rack.
Remove the system cover.
Removing the air shroud:
Hold the air shroud at both ends and lift the air shroud out of the system.
Removing a power supply unit:
Press the orange release latch and slide the PSU out of the system by using the PSU handle.
Removing the PIB:
Pull up on the plunger to disengage the PIB from the chassis floor.
Slide the PIB back and lift from the system .
NOTE:The numbers on the image do not depict the exact steps. The numbers are for representation of sequence.
Installing the PIB:
Align the guide slots on the PIB with the four hooks on the system.
Slide PIB in to the guide hooks till the plunger click in place .
NOTE:The numbers on the image do not depict the exact steps. The numbers are for representation of sequence.
Installing a power supply unit:
Slide the PSU into the PSU bay until the PSU is fully seated and the orange release latch snaps into place.
Installing the air shroud:
Align the air shroud with the standoff on the chassis wall.
NOTE:Route the cable properly to prevent the cable from being pinched or crimped.
Lower the air shroud into the system until it is firmly seated.
NOTE:The numbers on the image do not depict the exact steps. The numbers are for representation of sequence.
Replace the system cover.
If applicable, install the system into the rack.
Reconnect the peripherals and connect the system to the electrical outlet, and then power on the system.