Optionally, replicate the primary backup or retention to a replication protection storage for added protection. You can specify either scheduled replication or replication after backup completion.
Prerequisites
When creating multiple replicas for the same protection policy, it is recommended to select a different replication protection storage system for each copy. If you select a storage unit that is the target of another
objective for the same policy, the UI issues a warning.
Steps
Next to the primary backup or retention
objective, click
Replicate.
An entry for
Replicate appears to the right of the primary backup or retention
objective.
Under
Replicate, click
Add.
The
Add Replication dialog appears, with information in the left pane for each schedule that has been added for the primary
objective of this protection policy.
NOTE:PowerProtect Data Manager replicates backups for all the listed schedules. You cannot select individual schedules for replication.
Select a storage target:
Storage Name—Select a replication destination from the list, or select
Add to add
protection storage and complete the details in the
Storage Target window.
Storage Unit—Select whether this protection policy should replicate to a
New storage unit on the
protection storage, or select an existing storage unit from the list.
Network Interface—Select a network interface from the list, if applicable.
Retention Lock—Move the
Retention Lock slider to the right to activate retention locking for these replicas.
The retention lock mode setting comes from the configuration of the selected storage unit. When you activate retention locking, the
Retention Lock Mode field displays the corresponding storage unit setting.
The
PowerProtect Data Manager Administrator Guide provides more information about
protection storage.
Select when to replicate the backups or retentions:
To replicate after the backup finishes, move the
Replicate immediately upon backup completion slider to on.
For scheduled replication, move the
Replicate immediately upon backup completion slider to off, and then complete the schedule details in the
Add Replication dialog.
For replication of the primary backup, the schedule frequency can be every day, week, month, or
x hours.
For daily, weekly, and monthly schedules, the numeric value cannot be modified. For hourly schedules, however, you can edit the numeric value. For example, if you set
Create a Full backup every 4 hours, you can set a value of anywhere from 1 to 12 hours.
For asset types that support both synthetic full and full backup schedules, all replicas of the primary
objective inherit the retention period from the
Retain for value of the synthetic full and full backup schedules by default.
Click
Save to save your changes and return to the
Objectives page.
Next steps
Configure any remaining objectives. When you have configured all required objectives, click
Next.