omimssc 7.3 enrolement and migration to new management servers

Hi,

We are migrating to new management servers. The enrolement is targetted to a specific management server.

How to migrate this connection to one of the new management servers?

Is de-enrolement and adding all monitored objects again the only option?

 

br

charlez

Replies (7)
251

Charlez79,

 

You should be able to change enrollment of the server, as outlined on page 30 here.

 

Let me know if this works, or if you have any issues with it.

 

 


Chris Hawk
Social Media and Communities Professional
Dell Technologies | Enterprise Support Services
#Iwork4Dell

Did I answer your query? Please click on ‘Accept as Solution’
‘Kudo’ the posts you like!
237

It's in my case not possible to change the management server, the SCOM MS FQDN box is grayed out and can't be edited.

 

222

Hi @Charlez79,

 

We might need to check the configuration why it was grayed out, we'll be right back to find if there is a way to edit the information box. 


DELL-Joey C
Social Media and Communities Professional
Dell Technologies | Enterprise Support Services
#IWork4Dell

Did I answer your query? Please click on ‘Accept as Solution’. ‘Kudo’ the posts you like!

2 Bronze
2 Bronze
157

any update on this?

153

Hi @Charlez79,

 

It seems that there is no other way than to de-enrole and adding back the monitored devices again. Unfortunately, engineering has confirmed that the option to change the FQDN is not editable. They have submitted the request to amend the documentation. 


DELL-Joey C
Social Media and Communities Professional
Dell Technologies | Enterprise Support Services
#IWork4Dell

Did I answer your query? Please click on ‘Accept as Solution’. ‘Kudo’ the posts you like!

2 Bronze
2 Bronze
152

Nice, adding +200 servers manually again. 

Great software...

2 Bronze
2 Bronze
141

If SCOM Management Group has more than 1 Management servers and  if any Management server is down, or removed, the load will be distributed to next available Management server in the Management Group, :- in this case we can use Synchronize option, to add all the data of the devices discovered in the
enrolled SCOM with OMIMSSC 7.3, when we re-enroll, so that automatically we can add all the Servers with out any manual effort 

Please refer the link below for steps 

Dell EMC OpenManage Integration Version 7.3 with Microsoft System Center (OMIMSSC) for System Center...:

Page 64 has details steps

-Kiran P, 

#iWork4Dell