Hi all,
A CX3-80 is connected to HS21 Blades through 2 integrated brocade
switches; I would like to add a new Ibm P570 in the system. When
I set the zoning and activate Connectivity Status I do not see the new
machine except if I remove the blades in the configuration.
Does that mean that Blades (with Qlogic Hba) and P570 (with Emulex
Hba) cannot function together ? Did anyone faced the same problem ?
What could be the cause/solution.
Thanks in advance.
Consty
A CX3-80 is connected to HS21 Blades through 2 integrated brocade
switches; I would like to add a new Ibm P570 in the system. When
I set the zoning and activate Connectivity Status I do not see the new
machine except if I remove the blades in the configuration.
Does that mean that Blades (with Qlogic Hba) and P570 (with Emulex
Hba) cannot function together ? Did anyone faced the same problem ?
What could be the cause/solution.
Thanks in advance.
Consty
Consty
232 Posts
0
February 14th, 2008 04:00
Thanks
Consty
dynamox
2 Intern
2 Intern
•
20.4K Posts
0
February 14th, 2008 04:00
dynamox
2 Intern
2 Intern
•
20.4K Posts
0
February 14th, 2008 05:00
Consty
232 Posts
0
February 14th, 2008 06:00
How to refresh the array ? Is it from Navisphere ?
Thanks
dynamox
2 Intern
2 Intern
•
20.4K Posts
0
February 14th, 2008 06:00
Consty
232 Posts
0
February 14th, 2008 06:00
Thanks
dynamox
2 Intern
2 Intern
•
20.4K Posts
0
February 14th, 2008 06:00
kelleg
4.5K Posts
0
February 14th, 2008 11:00
How do you connect the new server to the intergated blade switch? Do you see it logged in on the switch? Can an intergrated switch have external connections from another server?
What does the blade manufacture say about this?
regards,
glen kelley
Consty
232 Posts
0
February 15th, 2008 00:00
It worked, seems the solution was to refresh the array.
Regards
Consty
Consty
232 Posts
0
February 15th, 2008 00:00
Answer is YES
2) And this is where you zone the blade servers to the clariion?
Answer is YES (as an external switch)
3)How do you connect the new server to the integrated blade switch?
Answer is the integrated swith has 6 external connexions (ports).
4) What does the blade manufacture say about this?
I don't understand the question.
Anyway, the integrated switch has the same function as an external one,
the only difference is that Blade servers are connected to it through internal
connexions and the rest (CX, external servers) are connected via external ports.
Regards
Consty
AranH1
2.2K Posts
0
February 15th, 2008 08:00
I don't understand the question.
In other words you have a host-to-switch-to-switch-to-array connection. So how are you managing the switch-to-switch connection? Are you zoning on the blade-integrated switch and on the core SAN switch? Are you using ISL?