What is the Procedure for DMX - DMX migration ..What are the steps we need to involve.. Wht are the things we need to do before starting the migration.

2 Intern

 • 

20.4K Posts

December 15th, 2010 07:00

it all depends, how close are the two boxes, what kind of software do you have (SRDF, Open Replicator)...what OSs

5 Practitioner

 • 

274.2K Posts

December 15th, 2010 13:00

You need a PM (Project Manager).

Than IDE, SA, and FSS, can be assign to the project.

Discussion of type of hardware, bin creation for the new array with your input.

list of devices tobe migrate, testing, cutover schedule.