as described in SC-Series-Synchronous-Replication-and-Live-Volume-Dell-EMC-2017 i´ve configured the live volumes with ha + auto fail-over on two mid-range SCvXXXX.
This the first time for me using the live volume feature.
I´ve zoned the esxi hosts 6.0 to every vWWN (source and target compellent).
i deployed two datacollectors/dsm (prim. and sek.)
I configured the volumes for auto-failover and ha, no fail-back
Everything showed "up and running". My test was now to pull the target-cables (fc) of the prim. system. The test-esx lost the connection to the lun. What was going wrong?
- Do i have to map the target lun (named "lv of lun") also to the esx-hosts? While the system works in normal state before?
I see you have deployed 2 data collectors, but you do not mention if you deployed a tiebreaker. See page 52 of the Synchronous Replication and Live Volume Best Practices. Also, it is recommended to use Fixed for the MPIO in VSphere per page 45 of the guide.
Was this test even realistic or does disconnecting the front cabling not bring a fail-over to the secondary side? If a network connection is lost then no auto failover will occur. This was shown in the Dell Storage SC Series 6.7 Live Volume Automatic Failover video http://en.community.dell.com/techcenter/extras/m/white_papers/20441883
What do you suggest for testing to show auto-failover to a customer (without "stressing" the hardware)? In that video they demonstrated by rebooting both controllers on the Primary Site. I am not sure that is an option for you.
What about server objects under "servers" of the secondary system? Do I even have to create the servers (initiators) there? Yes, for proper testing they should be configured for connection
thank you for the document and the note with the "tie breaker".
I forgot to mention the tie-breaker and of course installed it. Please note that my test was to remove the front-end by disconnecting the front wiring of the primary site. Included in front cabling: Target ports for servers (ESXi hosts) and for replication.
Tiebreaker was displayed as online. All other states were green according to primary dsm/dc. Essential questions for my part are now:
Was this test even realistic or does disconnecting the front cabling not bring a fail-over to the secondary side?
What do you suggest for testing to show auto-failover to a customer (without "stressing" the hardware)?
What about server objects under "servers" of the secondary system? Do I even have to create the servers (initiators) there? I thought that in case of a fail-over it is enough that the servers on the primary are known.
The Tiebreaker should be located at a third autonomous site which can monitor both the Primary and DR sites. It should be configured when setting up Live Volume with Auto Failover.
DELL-Bob Mi
2 Intern
•
230 Posts
11580
1
Posted April 14th, 2018 10:00
I see you have deployed 2 data collectors, but you do not mention if you deployed a tiebreaker. See page 52 of the Synchronous Replication and Live Volume Best Practices. Also, it is recommended to use Fixed for the MPIO in VSphere per page 45 of the guide.
http://en.community.dell.com/techcenter/extras/m/white_papers/20439310/