I have three N3000 switches(N3048*2, N3024P*1) and now I used stack for these switches, after configurated I found some of stack interface link status is down, how can I setup these link status to up?
Have you tried "stack-port twentygigabitethernet 1/0/2 no shutdown"?
In normal circumstances, you need not do any configuration on stacking ports, but in this case, try using the command above to try enable the port.
Could you confirm your cabling topology, would that be:
● The bottom mini-SAS port on Unit 1 is connected to the top mini-SAS port on Unit 2. ● The bottom mini-SAS port on Unit 2 is connected to the top mini-SAS port on Unit 3. ● The bottom mini-SAS port on Unit 3 is connected to the top mini-SAS port on Unit 1.
I would suspect that N3024P is not supported in the stacking, as it's a POE switch which needs a deliverance of 62W power, which N3048 is unable to support. Could you try both N3048 only and check if the stacking works.
If you already checked the cables and they are ok and you were not able to use the suggested command I should advice you to check the configuration. Maybe someting in the configuration is preventing this ports to go up.
flyfish712
1 Rookie
•
23 Posts
1470
1
Posted June 23rd, 2022 00:00
Hello,
The issue has been fix, just running command:
# Configure
# Stack
# No stack-port Tw1/0/2 shutdown
Thank you guys for help.