UNSOLVED
sql 2012 22000 IOPS
Hi,
i am new to emc and i am looking for some advice on the setup of our 5500. we have a requirement for an sql database to have up to 22000 iops and we are also looking to use the fast vp. we would like to to mix 2 types of drives in one group. i was thinking 10 200gb SSD drives and 8 1TB 10K sas drives (to accommodate other servers).
Is it possible to to add 10 SSD and 8 qtb drives to create a pool?
If this is possible i was thinking of presenting 2 2TB luns to my vmware system. once workloads are running the fast vp will detect and move high used blocks to the ssd tier? Have i got this totally wrong or am i on the correct track?
thanks
Responses (1)
Solutions (0)

Roger_Wu
6 Operator
•
4025 Posts
130
0
Posted June 5th, 2014 05:00
You can refer to the whitepaper
http://www.emc.com/collateral/white-papers/h12341-sqlserver-bp-wp.pdf
For example:
Other useful whitepapers:
SQL Server Analyzing Characterizing and IO Size Considerations
http://www.emc.com/collateral/white-papers/h11257-emc-performance-optimization-sql-server-wp.pdf
http://www.emc.com/collateral/hardware/white-papers/h10507-mission-critical-sql-server-2012.pdf
http://www.emc.com/collateral/hardware/white-papers/h10738-perfrmnce-aclrtion-sqlsrvr2012.pdf