Set Mtree-replication to read-write
Hi folks,
I have a question regarding an Mtree replication which I did set up to do a NetWorker migration.
I have an old and a new Data Domain. I established an Mtree replication part between the both systems. The replication did send all the data over to the new Data Domain but the Mtree path is now in the state „read-only“.
How can I change it to „read-write“? Do I have to break the replication pair like described in this article:
https://community.emc.com/docs/DOC-39089
Cheers,
beacon
0 events found
No Events found!


jayjay982
1 Rookie
•
48 Posts
0
October 15th, 2018 23:00
Hi Pushpendra,
thanks for your reply.
Do I have to break the replication on the source or destination Data Domain?
Are there additional steps to perform or will the Mtree on the destination side be read-write right after the break operation?
Thanks,
beacon
DELL-Sam L
Moderator
•
7.9K Posts
•
21 Points
0
October 18th, 2018 10:00
Hello beacon,
You want to break the destination Mtree.
Please let us know if you have any other questions.