Unsolved

This post is more than 5 years old

3 Posts

466

March 17th, 2010 20:00

SMC: Can one user Commit the "Active Tasks" which have been created by different USER?

Hi,

In SMC,

The userID "userA" creates a few "active tasks", none of other userID's seem can Commit these tasks...

Did anyone experence this kind of issue before? Is there any solution?

Thanks and regards,

Xin

6 Operator

 • 

2.1K Posts

March 18th, 2010 12:00

The active tasks are specific to each user. Is there something specific you are trying to use this functionality for? There may be a different way of achieving the same thing.

131 Posts

March 18th, 2010 13:00

I am sorry but is there old user leave the job?

3 Posts

March 21st, 2010 15:00

Hi Allen,

Thanks for the reply.

we want to do something like: one of our colleague creates the job in config session on the previous day, then then another person can run it in early morning next day... Is this achievable?? what is the way to do it?


Cheers,

Xin

6 Operator

 • 

2.1K Posts

March 22nd, 2010 08:00

This probably isn't the answer you want to hear, but the way to do what you are talking about is to use ControlCenter instead of SMC. I don't think there is any way to do it in SMC unless you have both users log in with the same ID. I know in our environment that would be an absolute violation of security as all activities need to be clearly traceable back to an individual.

3 Posts

March 22nd, 2010 14:00

Hi Allen,

Yes, I guess that is the case. Many thanks anyway!!


Cheers,

Xin

2 Posts

May 19th, 2010 16:00

Is this going to be fixed in a future release?

Regards

JO

No Events found!

Top