need some steps , we are doing SAN migration from MCDATA ED6064 to Brocade DCX . after SAN migration we are planning to do Storage Migration . So right now we are in the process of Site Survey or Remediation process. After that need to know some steps regaring SAN migration. I worked on Brocade for zoning purpose but I am not sure abt this SAN migration process... just need some help ..
coming to my environment we have 4-DMX 4 , 4-CLARiiONs , and now 2- VMAX s are coming with 5875 (Fast-VP) & coming to SAN we have 2 McData ED6064 . around 400 servers are connected to this Switch. Our plan is to take off this ED6064 and USE Brocade DCX. we have some other McData switches Older versions, but we are trying to migrate SAN ( ED6064 to DCX) than they will plan to do storage . DCX is fully configured and ready . So what is my major task is going to be??
cold cutover of 400 servers at once is probably out of the question so i am thinking that you will need to ISL ED6064 and DCX unless you have enough available ports on DMX4 /Clariions that you could connect to DCX and simply swing the hosts over.
dynamox
11 Legend
•
20419 Posts
•
87439 Points
1367
0
Posted January 28th, 2011 10:00
take a look at this document
Connectrix Manager Data Center Edition Professional, Professional Plus, and Enterprise User Guide 10.4.3 A07