In a general sense there is no pre-check prior to adding node to a cluster, however I personally think it is a good idea to have a burn period of new hardware. What I mean is, turn the nodes on do not plug in any IB cables, and create a cluster of 1 to sit and spin its disks for a day or two. This would help to catch any possible hardware failures that may occur due to any possibly rough handling during shipping and what not.
Just a suggestion. Many customers simply add nodes when they get them, but I think a burn period is good so that the risk of service interruption due to any possible early hardware failures is reduced. You can then reformat the nodes and add them to the existing clusters once this is done.
addisdaddy20
65 Posts
742
0
Posted February 2nd, 2016 08:00
In a general sense there is no pre-check prior to adding node to a cluster, however I personally think it is a good idea to have a burn period of new hardware. What I mean is, turn the nodes on do not plug in any IB cables, and create a cluster of 1 to sit and spin its disks for a day or two. This would help to catch any possible hardware failures that may occur due to any possibly rough handling during shipping and what not.
Just a suggestion. Many customers simply add nodes when they get them, but I think a burn period is good so that the risk of service interruption due to any possible early hardware failures is reduced. You can then reformat the nodes and add them to the existing clusters once this is done.