you can use SANCopy to push from VNX to VMAX3. Host can remain online during initial copy but will need to be shutdown to perform final copy. For hot pull you will need to shutdown the host on VNX, initiate pull operation on VMAX and start the host there.
One question, in our configuration the boot lun of the production server is also from the VNX.
So, if we go for the Open replicator with below high level plan.
1) Zone the VMAX dir. ports and VNX SP ports.
2) Discover the VNX source luns in VMAX.
3) Create the session files for VMAX - VNX luns as per syntax.
Shutdown the Production server. and unmap the VNX source luns.
4) Start the HOT PULL operation with donor update option.
5) Map the VMAX control luns to Production server.
6) Make the Production server up.
And using " copy on first access " algorithm. The server will boot seamlessly without any issue and copy all the urgently required blocks first those are required first for making the server up and then will continue for data copyfor remaining luns.
Is my understanding correct for boot lun and overall HIGH level plan.
If you are migrating boot luns as well as data luns my preference is to use two sessions, one for the boot lun and one for the data luns. When the host is offline start both sessions and when the boot lun session is complete start the host. I am not a fan of booting a host when it's boot lun is in the process of being migrated. In theory the latency shouldn't be that bad for host access to the boot lun during an open replicator migration but I have seen it cause issues enough times that avoid it.
i looked in elab navigator and could not find where SANCopy between CX4 and VMAX3 is supported (at least officially). I do see that Open Replicator hot/cold pull is supported so that's an option as well.
I would talk to your local account team, maybe you can get an RPQ and use SANCopy to VMAX3 migration ..or just use OR.
dynamox
11 Legend
•
20419 Posts
•
87439 Points
2058
1
Posted April 17th, 2015 03:00
you can use SANCopy to push from VNX to VMAX3. Host can remain online during initial copy but will need to be shutdown to perform final copy. For hot pull you will need to shutdown the host on VNX, initiate pull operation on VMAX and start the host there.