We're planning to move 10 FC DAE's from CX3-80 on to our new CX4-960 system.
CX4-960 is running Rel 29 and has 5 DAE's with id's 0_0,0_1,1_0,2_0,3_0.
CX3-80 is running Rel 26 patch 31.
1.Need your input on what pre-checks need to be completed?
2.After mounting DAE's on to CX4-960 will it automatically pick up Enclosure ID's or need to set it manually? what would be the best practise for doing this?
Some of the first things to check is are there any 2G disks in the DAE's you are moving? If there are, you will want to isolate those DAE's to one bus so the other buses can run at 4G. Also are these DAE's your moving all DAE2p & DAE3P?
Also make sure that you unbind all raid groups and hot spares on those CX380 DAE's before removing them.
How are your current DAE's racked? can i assume that starting from the bottom, they are 0_0, 1_0, 2_0, 3_0, 0_1? If so then i would recommend the following order so that you dont have to purchase longer backend cables.
1_1, 2_1, 3_1, 0_2, 1_2, 2_2, 3_2, 0_3, 1_3, 2_3 So your rack will look like this from the back:
TOP
2_3
1_3
0_3
3_2
2_2
1_2
0_2
3_1
2_1
1_1
0_1 Current
3_0 Current
2_0 Current
1_0 Current
0_0 Current
BOTTOM
You will need to set the enclosure ID for each. I would recommend that you do one at a time and use the NST/USM. Rack the DAE and apply power to one side. Do not attach any BE cables. Set the EnclosureID and then the BE cables.
I would also disable your email home on the CX4-960 untill your done to avoid a lot of emails.
all DAE3P/DAE4P enclosures ? You will need to set enclosure ID with a pencil or something sharp. Use NST and it will walk you through connecting all the cables and such. I would also decommission those 10 DAEs cleanly before you disconnect them (delete all LUNs, RAID groups, hot spares that use those DAEs)
Thanks a lot Kenn and Dynamox this inputs are really helpful. The CX4 rack houses two 5300 switches on the top, so I would need to reduce some DAE's than, we will use CX3-80 rack.Was thinking to disconnect CX3-80 SPE, SPS and DAE-OS and install some DAE's in that space will that work?
We won't be able to move the DAE-OS but is there a possibility to move remaining 146GB 15K disks from this enclosure and install them in a enclosure consisting of 300GB 15K disks?
so CX3 is going away completely ? I am sure you can re-use EMC 40U rack for CX4 expansion. Yes, you can put different capacity FC drives in the same DAE , obviously you would not want to bind them in a RG with 300G drives.
Jim, that support article is a litle wierd. First, none of the senarios show going from CX3 to CX4. all the issues with the zero mark are from CX4 to Cx3. but at the end it say that moving disks from CX3 to CX4 (vise versa) can lead to data lose.
I can tell you from personal experience, i just finshed a 6 month migration project in which i moved 12 FC and SATA DAE's from a CX380 and placed them on (2) CX4's. Then recarved them up and the lun's have been in production for months with out any COH or soft media errors.
I think that article has a typo in it. I understand taking a disk that was zeromarked on a CX4 and putting it in a CX3 would be bad
encl id depends on where you are going to place them on the bus, i would try to balance them between the available buses. Hopefully you have long cables that can stretch between the two racks.
kenn2347
4 Apprentice
•
542 Posts
1245
1
Posted January 16th, 2011 07:00
Some of the first things to check is are there any 2G disks in the DAE's you are moving? If there are, you will want to isolate those DAE's to one bus so the other buses can run at 4G. Also are these DAE's your moving all DAE2p & DAE3P?
Also make sure that you unbind all raid groups and hot spares on those CX380 DAE's before removing them.
How are your current DAE's racked? can i assume that starting from the bottom, they are 0_0, 1_0, 2_0, 3_0, 0_1? If so then i would recommend the following order so that you dont have to purchase longer backend cables.
1_1, 2_1, 3_1, 0_2, 1_2, 2_2, 3_2, 0_3, 1_3, 2_3 So your rack will look like this from the back:
TOP
2_3
1_3
0_3
3_2
2_2
1_2
0_2
3_1
2_1
1_1
0_1 Current
3_0 Current
2_0 Current
1_0 Current
0_0 Current
BOTTOM
You will need to set the enclosure ID for each. I would recommend that you do one at a time and use the NST/USM. Rack the DAE and apply power to one side. Do not attach any BE cables. Set the EnclosureID and then the BE cables.
I would also disable your email home on the CX4-960 untill your done to avoid a lot of emails.