I this a single switch or part of some Fabric (which has more than one switches). If its a single switch. 1. Login to the admin Web Page of 2400. 2. Download the config of the switch to a file on a PC. 3. Login to the admin console of the new switch upload the file to the new switch. 4. Enable the new config. 5. Connect the Servers and Storage one at a time to the switch and verify if the server can see storage thru the new paths. If all the servers are configured in a High Availability configuration you wont need downtime. This is a very brief action plan.. Let me know if its not clear. I will try and find some Doc for the same.
Navin-Swn_9
66 Posts
531
1
Posted June 12th, 2007 03:00
1. Login to the admin Web Page of 2400.
2. Download the config of the switch to a file on a PC.
3. Login to the admin console of the new switch upload the file to the new switch.
4. Enable the new config.
5. Connect the Servers and Storage one at a time to the switch and verify if the server can see storage thru the new paths. If all the servers are configured in a High Availability configuration you wont need downtime.
This is a very brief action plan.. Let me know if its not clear. I will try and find some Doc for the same.