UNSOLVED

mpi2

updated

19 years ago

M

mpi2

2 Intern

•

215 Posts

0

557

December 17th, 2007 04:00

Migration Taskplan RMSE to RM

Hy all,

At the customer we have RMSE 3.1.0.4 installed in a Windows 2003 64bit 3-Node Cluster. One MountHost for the Clone.
For the Upgrade to RM 5.0 I would like that the mountServer will be the RM Server and (logically clear) the RM clients the cluster nodes.
How can I make sure that the Database will be migrated to the mountserver and the clients will be the cl-nodes? (I know the setup detects the RMSE installation)

thanks.
best regards
Manfred
  • mpi2

    2 Intern

    •

    215 Posts

    202

    0

    Posted December 18th, 2007 02:00

    I already read the document but one thing left unclear:
    Ok. I'll start with the mounthost that's ok --> and I will select migrate -> and then I select the server component. --> make the install..
    --> At my RM clients (cluster nodes) when I start the RM 5.x Setup will it prompt for "migrate" and do I have to select "Yes" or "No"?

    Thanks.
    best regards
    Manfred
  • mpi2

    2 Intern

    •

    215 Posts

    202

    0

    Posted January 1st, 2008 09:00

    Hi Kevin,

    Thanks for your response!
    No problem you are in time, I will start the migration the day after tomorrow. :-)

    thanks again and best regards
    Manfred