Changing The Component Sequence

You can view the Bundle Properties details of a bundle by double-clicking it or by clicking the Properties in the Task menu. You have the Name: , Version: , OS type: , Operating System: , Platforms: and Size: details of that particular bundle.

After you click the Component Sequence tab, the list of components for that bundle are displayed. You can move component up or down in the load order by selecting each component and using the Move Up or Move Down buttons. You can manually set the order in to a specific sequence using this function. With a logical order, you can apply the relevant components reliably with less number of system restarts. If you are not sure about the correct sequence, use the Default Order to install the components.

To change the sequence of the components:
  1. In the Dell Repository Manager screen, click My Repositories tab, select the repository to which you want to add the component, and click Open.
  2. In the Bundles tab, select the bundle you want to customize.
  3. Double-click the bundle. The Bundle Properties window is displayed.
  4. Click Component Sequence tab. The list of the components is displayed.
  5. In the Component Sequence window, select one of the following:
    • Move Up — Select the component that you want to deploy first and click Move Up to bring that component at the top.
    • Move Down — Select the component that you want to deploy later and click Move Down to bring that component down to that list.
    • Default OrderDefault Order is the order of the component added to the bundle or its order when it was imported from a catalog file.
    • NOTE: If you have already initiated a job (such as export updates to Lightweight Deployment package, exporting to Bootable ISO and saving the repositories to a local disk) and want to rearrange the sequence of the components, the changes are not going to reflect for the ongoing jobs.
    • NOTE: By selecting Move Up or Move Down you can change the Order by 1 with each click.
  6. Click OK. The Bundle content order window is displayed. The Bundle content order window prompts you to confirm the changes. The order of components in the bundle was changed. The Do you want to Save the changes? window appears for confirmation.
  7. Click Yes to continue or click No to exit the window.
  8. If you select Yes the Bundle Disclaimer window is displayed with the following message: You are about to modify Dell recommended bundle(s). Please test the bundle(s) before deployment if you want to continue. You have the list of bundle(s) displayed under the Dell Recommended bundles window.
    • NOTE: If you do not want to view the disclaimer, select the Do not show again during this session check box.
  9. Click Ok or click Cancel to exit without making any changes. Once you click Ok, the Please wait... dialog box appears while Saving component order changes... .

Rate this content

Accurate
Useful
Easy to understand
Was this article helpful?
0/3000 characters
  Please provide ratings (1-5 stars).
  Please provide ratings (1-5 stars).
  Please provide ratings (1-5 stars).
  Please select whether the article was helpful or not.
  Comments cannot contain these special characters: <>()\