Assuming a Centra Configuration in which it should contain 32Nodes, I'm wondering in what quantity should we place order for this part number? Is this part number contains 4 nodes, which mean we should place order for 8 number of this part#? or we are wrong?
CNR4N7MBAG4LP 4NODE 750GB MANF BASE LOW POWER G4 -
Also in case we want to place order with its new replacement?
CNR4N1FBAG4LP UNBUNDLED 4 NODE GEN4LP WITH 1TB DRIVES WITH 2 SWI
Moreover, I'm wondering if the Harddisks are included or should be ordered seperatedly?
Thanks
Best Regards
Phukon
337 Posts
0
July 12th, 2010 08:00
Hi,
If you already have the rack and the switches installed, you may be required to order the nodes individually. The details are in the following:
2.0 TB COMPUTE STORAGE ENGINE, SW LOADED
Please note: You may refer to the latest Hardware notes also verify the part numbers with your local vendor or the EMC sales team.
Good Luck.
East_TN_EMC
29 Posts
0
July 13th, 2010 06:00
Oh, and yes, these kits would include the hard-drives already installed in the nodes and properly imaged with Centrastar code.
East_TN_EMC
29 Posts
0
July 13th, 2010 06:00
Hello,
You would need to order the following:
CNR4N1FBAG4LP - Centera 4 node (1TB HDD) field base Gen4 Low Power
which is a base-cube with 4-nodes. It will have two cube switches and 4 4-TB nodes.
Then you would need 6 of the following:
CNR2N1FUPG4LP - Centera 2 node (1TB HDD) field installed upgrade unit Gen4 Low Power
each of which are a 2-node upgrade unit and does NOT contain cube switches.
This combination would give you ONE full Gen4 cube containing 16 nodes. If you want 32 nodes, you would ned to double everything.
If you just order the nodes by their individual part numbers, you would not have rail-kits, power cords, switches, ethernet cables and the various other pieces of hardware needed to rack-mount the cluster.
I suggest you contact your local EMC sales rep. so that your exact needs can be evaluated and they will be able it insure that all necessary parts and services are ordered to make sure you have a smooth and successful installation. The services sold will also make sure the Centera is implemented correctly with your application.
Jeff
Apex_Ops
89 Posts
0
July 29th, 2010 05:00
Hello,
I see you posted a question regarding ordering centera nodes and that your question in this post appears to have been answered. Was this a correct or helpful answer? If so could you please mark the question as Answered (helpful or correct)?
Rgds