Isilon Gen 5 to Gen 6 Migration -
Hello All,
Need assistance with directions on Migration from Gen5 to Gen 6
We have 3 node Gen 5 cluster at prod and DR sites and planning to migrate to 4 Gen6 H nodes. What is the best way to migrate to new nodes ? Can we add Gen6 nodes to Existing 3 node cluster and smart fail the old nodes
Could some one suggest and provide any relevant directions. Appreciate your help
DELL-Sam L
Moderator
Moderator
•
6.9K Posts
0
August 7th, 2020 16:00
Sprinklr Hello krishsna1213,
You can use either OneFS or SyncIQ to migrate over your data. Here is the guide to each tool.
OneFS
https://dell.to/3ihiWa0
SyncIQ
https://dell.to/3ikWcWJ
Phil.Lam
1 Rookie
1 Rookie
•
567 Posts
0
August 14th, 2020 14:00
@krishsna1213,
To clarify:
OneFS migration if all nodes are Infiniband backend.