Hi,
I have 4 6248 units. connected according to page 5 here :
http://www.dell.com/downloads/global/products/pwcnt/en/pwcnt_stacking_switches.pdf
the manual states that the units has to be brought up in a certain order master be turned on first and then the rest of the units .
what happens when I have power failure ?
from the little experience I had, it took several times of restarts to the units until all the network was reachable (sometimes other units took over as master etc etc.)
Thank you for any clarification.
Nedz.
0 events found
No Events found!


nedzdell
7 Posts
0
September 25th, 2013 06:00
Thank you for your reply.
in my scenario I have 4 switches connected via stacking cables.
today one of the switches ups failed and as soon as it got up all the remaining 3 switches became masters.
this also resulted in the network not being reachable for some of the clients
only bringing the switches back up at the right order fixed network availability.
I really don't mind other units being masters as long as the network keeps working.
any Idea on why this would happen ?