Hi,
Here is the user guide for rail installation and removal for the server: https://dell.to/2P0YJIQ
Szazi
2 Posts
July 27th, 2020 05:00
There is information on how to mount and pull the rails into the rack, but no information on how to remove the server from it
DELL-Charles R
4.7K Posts
July 27th, 2020 06:00
Hello Szazi,
The directions for removing the server are on page 2 of the PDF Joey provided:
Installing and removing the system
2. Follow the procedures in this section to remove the system from
the rack.
i. Rotate the slam latches upward, on each side of the
system, to release the system.
ii. Hold the sides of the system and pull it forward until the
inner slide rails are fully extended.
iii. Rotate and hold the server-lock latch while pulling the
system firmly to slide the standoffs to the front of the
J-slots.
iv. Lift the system out of the rack.
NOTE: To secure the system for shipment in the rack or for other
unstable environments, locate the screw under each slam latch
and tighten each screw by using Phillips #2 screwdriver.
Dell Support Resources
View All
Top
DELL-Joey C
Moderator
•
4.1K Posts
0
July 27th, 2020 02:00
Hi,
Here is the user guide for rail installation and removal for the server: https://dell.to/2P0YJIQ
Szazi
2 Posts
0
July 27th, 2020 05:00
There is information on how to mount and pull the rails into the rack, but no information on how to remove the server from it
DELL-Charles R
Moderator
•
4.7K Posts
0
July 27th, 2020 06:00
Hello Szazi,
The directions for removing the server are on page 2 of the PDF Joey provided:
Installing and removing the system
2. Follow the procedures in this section to remove the system from
the rack.
i. Rotate the slam latches upward, on each side of the
system, to release the system.
ii. Hold the sides of the system and pull it forward until the
inner slide rails are fully extended.
iii. Rotate and hold the server-lock latch while pulling the
system firmly to slide the standoffs to the front of the
J-slots.
iv. Lift the system out of the rack.
NOTE: To secure the system for shipment in the rack or for other
unstable environments, locate the screw under each slam latch
and tighten each screw by using Phillips #2 screwdriver.