DMX 4 microcode upgrade

Hello,

Could you tell me how long it takes to upgrade DMX4 microcode?

This include all preparation steps(healtcheck before after, EMC Grab and etc.).

Thank you.

100 Posts

December 12th, 2012 08:00

Thanks.

I'm new in symmetrix world, so can you explain me about CCA approval.

As far as i know CCA approval is needed when change something in bin file, but i've never created CCA request.

How to create CCA request..via powerlink or via Partner web site?

812 Posts

December 12th, 2012 08:00

Confirm from local team if CCA is required here or not. If it is an outfamily upgrade and CCA approval is involved, it takes normally 4-5 working days for approval.

And the healthcheck, grab analysis etc.. depends how fast it is performed. If you have less number of hosts attached, It can happen even in a single day.

812 Posts

December 12th, 2012 09:00

Change Control Automation (CCA) is performed by either by EMC engineer or partner only. It requires privileged powerlink access.

108 Posts

December 18th, 2012 01:00

The procedure to upload the code in DMX3/DMX4 is fully "online" and transparent to the user. It does not take any request to EMC or machine lock.