Unsolved
This post is more than 5 years old
1 Rookie
•
52 Posts
0
1674
March 26th, 2014 05:00
Move the Client to another Grid - failed
Hi All,
I am trying to move a client to another grid using client manager.
When I start the move it is getting failed with the below error :
Move Failed. Client Scheduled for 24 retries. Invitation failed.
Client Software Could not be contacted
Can you help me how to resolve this error. Please let me know if you need any more infomration.
Windows Client
GSAN Version : 6.1.1-87
Regards,
vamsi



Vamsi_P
1 Rookie
•
52 Posts
0
March 26th, 2014 05:00
Yes please, Move me there
SuhelaDighe
70 Posts
0
March 26th, 2014 05:00
Hi, the "EMC Forum" space is related to the event series. Which product is this question related to, so I can move it into the relevant support community?
SuhelaDighe
70 Posts
0
March 26th, 2014 05:00
WHICH support community? Which product do you have an issue with?
Vamsi_P
1 Rookie
•
52 Posts
0
March 26th, 2014 06:00
EMC Avamar
mpearson1
5 Posts
0
March 26th, 2014 19:00
My understanding how this works is the backups only are moved when you initiate the move via client manager without a way to view the process of the movement. I'm sure there is a process running on the Avamar grid with a log file. The client doesn't activate automagically to the destination grid after the move is complete. You may have to do this manually. If you do it manually check the backup and restore window and see if the client has any backups on the destination grid. It may have some if you were replicating though.
Are you initiating the move from the source grid? Is the client still activated with the source grid?
DELL-Leo
Community Manager
•
9K Posts
0
March 26th, 2014 20:00
Hey,
Please stop any backup or restore activities of the client on source grid before the client moving.
And please refer to "Moving clients to a new server" section of Avamar 6.1 Administration Guide on page 460.
Hope this helps!
Vamsi_P
1 Rookie
•
52 Posts
0
March 27th, 2014 07:00
Yes, I was doing in the same process. Migrating the backups of the clients from the source grid using Client manager. For many server it is completed and for few server, I am getting this error
Move Failed. Client Scheduled for 24 retries. Invitation failed.
Client Software Could not be contacted