This post is more than 5 years old
20 Posts
0
1474
September 21st, 2011 12:00
Job Summary Report
Hi,
Is there a way to remove failed jobs that have been rerun successfuly from the job summary report? For example, if a job ran and failed and was then successfully rerun this would just be reported as one completed and one successful job with no failures. The deduplicate operator seems perfect for this but will not work with the sources within the job summary report. Have I missed a standard report or do have I to do some pretty significant customisation?
Thanks.
No Events found!



DavidRussell1
141 Posts
0
September 22nd, 2011 00:00
Hi,
You are correct that there is no standard report to do this however the customizations to the standard report should be fairly simple. You would need to:
-open the Backup Job Summary report in the Report Editor and open the report item so that you can see the data sources and operators
- replace the first "Backup Statistics" data source and "Dummy" operator with the "Num Backup Jobs After Deduplication" data source which is in the Backup category. You will need to change the Interval on the data source (in the Times tab) to "No Interval" and change the Field label to be "Completed"
- modify the "Dummy" operator connected to the second "Backup Statistics" data source to also return the "Size" field by taking the tick out of the "Drop" column for that row
- replace the third "Backup Statistics" data source and "Dummy" operator with the "Num Failed Backup Jobs After Deduplication" data source which is in the Backup category. You will need to change the Interval on the data source (in the Times tab) to "No Interval" and change the Field label to be "Failed"
Kind Regards
David
David Russell
EMC Technical Support
charvey1
20 Posts
0
September 22nd, 2011 09:00
Thanks David, this gave me exactly what I needed.
Regards,
Chris
charvey1
20 Posts
0
October 24th, 2011 02:00
Hi David,
This works perfectly where the original and rerun job remain indentical. However, I have an example where the rerun job changes - the original has 8 separate filesystems in one job but the rerun is split into 8 separate jobs, one for each filesystem. Is there anyway to reconcile the 8 reruns to the original job so that if all 8 are successful it is not reported as a error?
Thanks
Chris
DavidRussell1
141 Posts
0
October 24th, 2011 02:00
Hi Chris,
Unfortunately not as DPA looks at the job field (which contains the name), along with some others, to determine if they are the same job and whether to deduplicate or not. If these don't match then DPA has no way of determining it is the same job and that it needs to deduplicate.
Thanks
David
David Russell
EMC Technical Support
charvey1
20 Posts
0
October 24th, 2011 09:00
Hi David,
Thanks for the prompt reply. Would I be correct in assuming this would also impact other reports, for exampe job being succussful/unsuccessful would be one of the criteria used by exposure reports? Just trying to explore other options in producing a report that would list clients not backed up in the previous day but not based on jobs due to the above problem.
Thanks again.
Regards,
Chris
DavidRussell1
141 Posts
0
October 25th, 2011 00:00
Hi Chris,
Yes this could affect other reports. For the exposure reports they will look back to the last successful full run of each job to see what the exposure is. So if the job was shown as Failed with a different job name, then it will mark the exposure as there, as it isn't able to determine there has been a subsequent successful retry, as the job name is different.
Thanks
David
David Russell
EMC Technical Support
charvey1
20 Posts
0
October 25th, 2011 06:00
Hi David,
Thanks for the information.
Regards,
Chris