Solved!
Go to SolutionD
dgrimmeissen
13 Posts
0
12790
November 12th, 2010 20:00
Question about PowerPath Migration Enabler for Windows 2008 Clusters
I have been using PowerPath Migration Enabler Host Copy to perform migrations from a CX3-20 to a CX4-120. It has worked great on my windows servers enabling me to do host-based migrations with zero downtime.
Now it comes to migrating the Windows 2008 clusters. I'm reading through the PowerPath Migration Enabler 5.5 User Guide and on pages 51-52 it discusses using PPME for clusters. The steps seem the same until it comes to step 8.
It says:
On Windows 2003 clusters when ready to commit the migration run "powermig commit" and you are finished.
On Windows 2008 clusters it says to first "bring the failover groups offline, stopping the applications", then run "powermig commit", and finally bring the failover groups back online.
Am I reading this correctly that I must bring the groups down in order to commit the migration, but I did not have to do so on 2003? If so, that is disappointing, because PPME has been great for all of my other migrations. I wonder why the groups have to be shut down in 2008 when they did not need to be in 2003.
Responses (0)