Hello all,

I am very new to Recoverpoint and need some help here .

Customer has plans to  run a DR test and would like to write to their secondary site and discard the changes done .

And after a month or so failover again , but this time they want to run on the DR for a week and then failback .So all the production activity will be running from DR site for a week .

What should be a proper DR plan  for both the activities .

Here is the set up -

FC connected VNX1 at both the sites (remote replication) replicating via RP (v4.4).Only two node oracle hosts are attached to the VNX .

There are 4 CG. Also, no SRM .

Please let me know what are the initial information that I need to collect and what be the strategy  to do a failover .

If possible please share some documents ot links pertaining to RP DR without using SRM .