Move node from one rack to another
Hi All,
I have a question for you. Hope somebody have some experience with that.
We have completed a CICM in a 5 cube centera, because All cube 1 and nodes from c002n01 to c002n12 have old GEN4 nodes and must be removed.
The migration finished fine but after remove the old GEN4 nodes, now we have a Rack with 4 GEN4LP (c002n13 to c002n16) nodes and another rack with the last new 6 nodes (c005n01 to c005n06).
I want to move the last c005n01 to c005n06 nodes to the first rack in poistions c002n06 to c002n12, to remove last rack form site, and have all nodes together.
Which is the best way to do that? Remove nodes from cluster and add it again? CICM?
Thanks in advance for your help.
Dario