Hi,
We have dual compellent sc8000 controllers on both primary and dr sites having 100mb pipe fore the async replication now I want to segregate replication traffic by creating another fault domain using 10gb iscsi ports but there is a question If i pause eplication and create new fault domain and reconfigure remote replication connection between storage and resume replication will it resume? or re-replicate all the volumes,Please guide me if anyone knew about it. Thanks.
No Events found!


mluethye
26 Posts
1
June 2nd, 2016 21:00
I would call support - but i'm pretty sure it will pickup where it left off. I'm 99% sure but the 1% of me says you should call support and confirm.
My thought process is sure the connection will be cut for a short period, but just like anything else (say a network issue or controller failure) when the connection resumes the replication continues.