moving drives from DR pool to prod pool on unity
Hi
We have a customer who is looking out to use Unused disks in a pool on unity (in this case Unity 600) and move it to another pool without disruption or damage to either pools ?
In our case we are planning to move to move disks from our DR pool to the prod pool for supporting our migrations.
Your help is highly appreciated.
Thanks
Krishna Prasad.S
Principle Engineer.
DELL EMC.
DELL_ChrisHolloway
125 Posts
0
December 17th, 2019 08:00
You can't remove disks from a pool on Unity. You'd need to evacuate all data from the DR pool, destroy the DR pool, re-configure the disks as required, then re-create the DR pool.