EMC SRDF
SRDF - Normally its the delta from R1 --> R2, (bi-directional). Its easier to take a SNAP or Clone of R2 and do the DR testing and just drop the clone / SNAP its much safer.
However, I have a client that only has the EMC source (R1) and a remote target (R2) without an R3 or R4 for DR exercise. For a DR Exercise they stop replication (R1 --> R2) prior to a DR Exercise, and use R2 during the DR Exercise, and update R2 during the DR Exercise,,
They do not purge R2 updated data after the exercise, but want to restart replication post exercise.
My question is; will SRDF just send the delta (build up from prod while replication was suspended) from R1 to R2, or will SRDF hiccup and cause the R2 files re-synched from the beginning??
I know this is a long question but I hope I gave you enough to answer.. I have team members that state only the delta will be pushed during the re-sync but it does not make sense to me.
Thanks