O upgrade do RCM do PowerFlex 4.x no RG HCI falha com o erro: Falha ao instalar VIBs

Summary: Falha no upgrade do RCM durante a instalação do VMware VIB, pois os arquivos necessários não estão mais no pacote RCM/IC.

This article applies to This article does not apply to This article is not tied to any specific product. Not all product versions are identified in this article.

Symptoms

Falha no upgrade do RCM. Falha no upgrade do RCM durante process_firmware_update:

Faça log-in no pod do thin-deployer e vá para deployment.log do depoyment_ID/Job_ID
ERROR [2025-01-31T07:52:00.660421] 677128: service_deployment.rb:6081:in `process_firmware_update': Encountered an error during firmware update: RuntimeError: env --unset=RUBYOPT --unset=GEM_HOME --unset=RUBYLIB --unset=GEM_PATH --unset=BUNDLE_BIN_PATH RUBYLIB=/opt/service/lib:/opt/asm-deployer/lib:/opt/puppetlabs/puppet/lib:/opt/dependencies/dell-asm-util/lib PATH=/usr/local/sbin:/usr/local/bin:/usr/sbin:/usr/bin:/sbin:/bin:/opt/puppetlabs/puppet/bin:/opt/puppetlabs/bin puppet asm process_node --debug --trace --filename /opt/Dell/ASM/deployments/Job-2b551cc3-f546-4765-9eee-6416de02b254-0-0/resources/rackserver-cxjswf3.yaml --run_type apply --statedir /opt/Dell/ASM/deployments/Job-2b551cc3-f546-4765-9eee-6416de02b254-0-0/resources --always-override rackserver-cxjswf3 failed; output in /opt/Dell/ASM/deployments/Job-2b551cc3-f546-4765-9eee-6416de02b254-0-0/rackserver-abcdef3.out

ERROR [2025-01-31T07:56:00.831433] 677128: service_deployment.rb:7229:in `finalize_firmware_update': Failed to update the server!
INFO  [2025-01-31T07:56:00.831570] 677128: service_deployment.rb:7234:in `finalize_firmware_update': Firmware update status: Error
ERROR [2025-01-31T07:56:00.875669] 677128: service_deployment.rb:675:in `process': Firmware update failed for Job-2b551cc3-f546-4765-9eee-6416de02b254-0-0
ERROR [2025-01-31T07:56:00.875864] 677128: service_deployment.rb:676:in `process': ["/opt/asm-deployer/lib/asm/service_deployment.rb:7238:in `finalize_firmware_update'", "/opt/asm-deployer/lib/asm/service_deployment.rb:6095:in `process_firmware_update'", "/opt/asm-deployer/lib/asm/service_deployment.rb:526:in `process'", "/opt/asm-deployer/lib/asm.rb:385:in `block in process_deployment'", "org/jruby/RubyArray.java:2025:in `each_slice'", "/opt/asm-deployer/lib/asm.rb:366:in `block in process_deployment'", "/opt/dependencies/dell-asm-util/lib/asm/util.rb:22:in `block in execute_async'"]
INFO  [2025-01-31T07:56:00.876253] 677128: service_deployment.rb:678:in `process': Status: Error

Do .out do host do ESXi, a instalação falhou durante a instalação dos seguintes componentes:

/opt/Dell/ASM/deployments/<JOB_ID>/rackserver-service_tag.out<>
** /opt/Dell/ASM/deployments/Job-2b551cc3-f546-4765-9eee-6416de02b254-0-0/rackserver-abcdef3.out **
Error: Failed to install VIB for
["https://10.92.113.140:443/httpshare/download/8aaa801394ba0c920194ba1b53b00004/vibs70/INT_bootbank_i40en_2.5.2.0-1OEM.700.1.0.15843807.vib__;!!LpKI!glu2235RWNPqShl_xs0gxErxlqUao3Xy5zb_dK_dKz6ireUNS8hD7XuE_BEHR6rXQHNZg5cpfSE5oolHSF-bVBu-6WY7ee0a$ [10[.]92[.]113[.]140]",
"https://10.92.113.140:443/httpshare/download/8aaa801394ba0c920194ba1b53b00004/vibs70/DEL_bootbank_dcism_5.3.0.0.3289-DEL.700.0.0.15843807.vib__;!!LpKI!glu2235RWNPqShl_xs0gxErxlqUao3Xy5zb_dK_dKz6ireUNS8hD7XuE_BEHR6rXQHNZg5cpfSE5oolHSF-bVBu-6RyLpejW$ [10[.]92[.]113[.]140]",
"https://10.92.113.140:443/httpshare/download/8aaa801394ba0c920194ba1b53b00004/vibs70/VMware_locker_tools-light_12.2.6.22229486-22348808.vib__;!!LpKI!glu2235RWNPqShl_xs0gxErxlqUao3Xy5zb_dK_dKz6ireUNS8hD7XuE_BEHR6rXQHNZg5cpfSE5oolHSF-bVBu-6SW0V3E0$ [10[.]92[.]113[.]140]",
"https://10.92.113.140:443/httpshare/download/8aaa801394ba0c920194ba1b53b00004/vibs70/INT_bootbank_ixgben_1.15.1.0-1OEM.700.1.0.15843807.vib__;!!LpKI!glu2235RWNPqShl_xs0gxErxlqUao3Xy5zb_dK_dKz6ireUNS8hD7XuE_BEHR6rXQHNZg5cpfSE5oolHSF-bVBu-6dkiwDeX$ [10[.]92[.]113[.]140]",
"https://10.92.113.140:443/httpshare/download/8aaa801394ba0c920194ba1b53b00004/vibs70/INT_bootbank_i40en_2.5.2.0-1OEM.700.1.0.15843807.vib__;!!LpKI!glu2235RWNPqShl_xs0gxErxlqUao3Xy5zb_dK_dKz6ireUNS8hD7XuE_BEHR6rXQHNZg5cpfSE5oolHSF-bVBu-6WY7ee0a$ [10[.]92[.]113[.]140]",
"https://10.92.113.140:443/httpshare/download/8aaa801394ba0c920194ba1b53b00004/vibs70/DEL_bootbank_dcism_5.3.0.0.3289-DEL.700.0.0.15843807.vib__;!!LpKI!glu2235RWNPqShl_xs0gxErxlqUao3Xy5zb_dK_dKz6ireUNS8hD7XuE_BEHR6rXQHNZg5cpfSE5oolHSF-bVBu-6RyLpejW$ [10[.]92[.]113[.]140]",
"https://10.92.113.140:443/httpshare/download/8aaa801394ba0c920194ba1b53b00004/vibs70/INT_bootbank_ixgben_1.15.1.0-1OEM.700.1.0.15843807.vib__;!!LpKI!glu2235RWNPqShl_xs0gxErxlqUao3Xy5zb_dK_dKz6ireUNS8hD7XuE_BEHR6rXQHNZg5cpfSE5oolHSF-bVBu-6dkiwDeX$ [10[.]92[.]113[.]140]"]: Error RbVmomi::Fault:VimEsxCLICLIFault: EsxCLI.CLIFault.summary

Error: Fault error message: [" [VibFormatError]", " ('<http.client.HTTPResponse object at 0xe3d7cbf310>', \"Not a valid ar file (magic=b'')\")", "  
filename = https://10.92.113.140:443/httpshare/download/8aaa801394ba0c920194ba1b53b00004/vibs70/VMware_locker_tools-light_12.2.6.22229486-22348808.vib__;!!LpKI!glu2235RWNPqShl_xs0gxErxlqUao3Xy5zb_dK_dKz6ireUNS8hD7XuE_BEHR6rXQHNZg5cpfSE5oolHSF-bVBu-6SW0V3E0$ [10[.]92[.]113[.]140]", " Please refer to the log file for more details."]

Debug: Host Maintenance mode = true

Warning: Host is in maintenance mode. Exiting Maintenance mode...

Error: Failed to install VIBs
/opt/puppetlabs/puppet/lib/ruby/vendor_ruby/puppet/util/errors.rb:157:in `fail'

Cause

O problema decorre do fato de que o arquivo VMware_locker_tools-light_12.2.6.22229486-22348808.VIB tem 0 bytes no arquivo RCM/IC porque a DELL não fornece mais esses arquivos. No entanto, eles estão disponíveis no depósito de patches da VMware, mas foram ignorados durante o processo de atualização. 

Resolution

Qualquer uma das soluções alternativas a seguir pode ajudar.

  1. Como carregar o arquivo VIB usando o upgrade de componente único (SCU):
    1. Extraia VMware_locker_tools-light_12.2.6.22229486-22348808.VIB do depósito de patches da VMware.
    2. Habilite o upgrade de componente único (SCU).
      Faça log-in em qualquer um dos nós do MVM e execute o seguinte:
      kubectl patch hr asmmanager -p '{"spec":{"values":{"appConfig": {"modify_compliance":"true"}}}}' -n powerflex --type=merge
    3. Vá para a versão de conformidade do → da interface do usuário da PFMP → Selecione o pacote RCM → pacote de software → selecione "Pacote de software do ESXi x.x" e clique em Exibir → Selecione "VMware Tools VIB for Windows and Linux guest" na lista de componentes e clique em Modify.
      Carregue o arquivo VMware_locker_tools-light_12.2.6.22229486-22348808.VIB e, em "Nova versão do pacote", mencione a seguinte versão: 12.2.6.22229486-22348808. A versão aqui seria a mesma que você vê em 'Versão do pacote'. Clique em Prosseguir:
      Nota: Você vê esse componente com uma tag 'Modified'.

       

    4. Execute o upgrade do RCM/IC.
       
  2. Instalar manualmente o VIB do VMware Tools:
    1. Instale manualmente o VIB extraído do pacote ZIP de atualização off-line baixado da Broadcom:
      # esxcli software vib install -v /<path_to_the_depot>/VMware_locker_tools-light_12.2.6.22229486-22348808.vib
      Installation Result
         Message: Operation finished successfully.
         Reboot Required: false
         VIBs Installed: VMware_locker_tools-light_12.2.6.22229486-22348808
         VIBs Removed: VMware_locker_tools-light_12.3.5.22544099-22545121
         VIBs Skipped:
    2. Execute o Inventory para o host do ESXi acima na guia "Resource".
    3. Verifique a conformidade. O VIB instalado é marcado como compatível e ignorado durante o processo de upgrade.
    4. Execute o upgrade do RCM/IC.
       
  3. Repita o upgrade da RCM.  A segunda tentativa deve ser bem-sucedida.

Additional Information

Versões afetadas

PFMP 4.x

Correção feita na versão

PFMP 4.6.1 

Affected Products

PowerFlex rack RCM Software
Article Properties
Article Number: 000283204
Article Type: Solution
Last Modified: 02 Jun 2025
Version:  2
Find answers to your questions from other Dell users
Support Services
Check if your device is covered by Support Services.