Add the SC100/SC120 Expansion Enclosures to the A-Side of the Chain

Connect the expansion enclosures to one side of the chain at a time to maintain drive availability.

  1. Remove the A-side cable (shown in orange) that connects storage controller 1: port A to storage controller 2: port B. The B-side cable continues to carry IO while the A-side is disconnected.
    Figure 1. Remove the A-Side Cable from the Storage ControllersDisconnect the A-side cable that interconnects the .
    1. Storage system
    2. Storage controller 1

    3. Storage controller 2

  2. Cable the expansion enclosures to the A-side of the chain.
    1. Connect a SAS cable from storage controller 1: port A to the first expansion enclosure in the chain, top EMM, port A.
    2. Connect a SAS cable from storage controller 2: port B to the last expansion enclosure in the chain, top EMM, port B.
    Figure 2. Connect the A-Side Cables to the Expansion EnclosuresCable the to the A-side of the chain.
    1. Storage system
    2. Storage controller 1
    3. Storage controller 2
    4. Expansion enclosure 1
    5. Expansion enclosure 2

Rate this content

Accurate
Useful
Easy to understand
Was this article helpful?
0/3000 characters
  Please provide ratings (1-5 stars).
  Please provide ratings (1-5 stars).
  Please provide ratings (1-5 stars).
  Please select whether the article was helpful or not.
  Comments cannot contain these special characters: <>()\